At a Toyota stamping facility, metal sheets were sticking together during the stamping process, causing production delays and defective parts.

Toyota

Toyota

At a Toyota stamping facility, metal sheets were sticking together during the stamping process, causing production delays and defective parts.

Challenge

Challenge

Bulk sheets failed to separate properly, leading to feeder jams, unplanned downtime, and increased scrap rates.

 

The intermittent sheet separation not only slowed cycle times but also risked damaging equipment.

Solution

Solution

Industrial Magnetics sheet fanners were installed to ensure each metal sheet was individually separated from the stack before feeding into the press.

Results

Results

Downtime Reduction: Feeder jams eliminated, slashing unplanned stoppages

 

Quality Assurance: Scrap rates reduced, ensuring consistent, defect‑free stamping

 

Throughput Boost: Production speed increased, fully supporting just‑in‑time schedules